Twelve questions drawn from the reasons organisations actually fail a Stage 2 audit, answered honestly in about five minutes.

Answer twelve questions about your management system and see where a certification auditor would find gaps. The questions come from documented Stage 2 failure modes, not from a generic checklist. The readout appears once all twelve are answered.

This is a self-check, not an assessment and not a pre-audit. It runs in your browser, and no result from it means anything to a certification body. Answer as your operation actually runs rather than as the procedure says it should, or the output is worthless. To keep the readout, print the page or copy it.

  1. 01 · Clause 4.3

    Is the scope of your management system written down, and does it match what the site actually does?

    An auditor reads the scope statement, then walks the floor. A scope or an exclusion the operation cannot support is one of the five standard reasons a Stage 2 fails.

  2. 02 · Clause 6.1.2 and 6.1.3NEW IN ISO 9001:2026

    Are opportunities managed separately from risks, each with an owner and an outcome?

    The 2026 edition splits the single risks and opportunities clause in two. An opportunities column appended to the risk register, with no owner and no outcome, is the usual state and it no longer reads as compliance.

  3. 03 · Clause 5.2.1(e)NEW IN ISO 9001:2026

    Does your quality policy connect explicitly to your context and strategic direction?

    New in the 2026 edition. Most policies were written to be framed on a wall and say nothing about where the business is going, which is exactly what the clause now asks for.

  4. 04 · Clause 6.2

    Are your objectives measurable, with a plan naming what will be done, by whom and by when?

    Clause 6.2.2 asks for the plan, not just the objective. An objective with no named owner and no date is a statement of intent, and the auditor will say so.

  5. 05 · Clause 9.1

    Is process performance measured, with data that somebody actually looks at?

    If nothing is measured, clause 9.1 has nothing to examine and neither does management review. This is the second of the five standard Stage 2 failures.

  6. 06 · Clause 9.2

    Have internal audits been completed to your documented, risk-based programme and, before a first certification, has one full cycle covering the whole scope been completed?

    An auditor cannot verify a system that has never checked itself. After the first cycle, coverage follows the programme's risk basis across the certification cycle rather than a full sweep every year. Stage 1 checks that the first cycle and a management review are done, so a missing cycle stops the process before Stage 2.

  7. 07 · Clause 9.2.2(c)

    Did every internal audit avoid the auditor auditing their own work?

    In a small team the quality manager usually owns document control and also audits it. That is an impartiality finding against the whole programme, which is worse than a finding against document control.

  8. 08 · Clause 9.3

    Has a management review been held with the required inputs, and are its outputs recorded as decisions?

    Minutes that record attendance and a general discussion do not evidence the inputs listed in 9.3.2 or the outputs required by 9.3.3. The agenda should mirror the clause.

  9. 09 · Clause 10.2

    Do your corrective actions record a root cause and an effectiveness check, not just the fix?

    Clause 10.2 asks for the cause, the action and evidence the action worked. Most logs in this market carry the fix alone, and it is the third of the five standard failures.

  10. 10 · Clause 7.5

    Is the revision in use at the point of use the current one, everywhere?

    The most common document control finding is an obsolete revision in active use, usually a laminated form on a wall that outlived the master it was printed from.

  11. 11 · Clause 7.1.5 and 7.2

    Can you retrieve competence records and the calibration register in minutes, with certificates attached?

    Both are on the list an auditor asks for before the site walk. Records that exist but cannot be found in reasonable time are a finding in their own right.

  12. 12 · Clause 8.4

    Are outsourced processes inside your scope controlled and evidenced, with criteria and re-evaluation?

    Outsourced work inside the scope but uncontrolled is the fourth standard Stage 2 failure. Maintenance, calibration, laboratory testing and transport are the usual gaps.

0 of 12 answered

The readout appears here once all 12 questions are answered. It runs in your browser: print the page or copy the readout to keep it.

/

About the check

Q01

Is there a pass mark?

No, deliberately. A number out of twenty-four is not a certification outcome and treating it as one would be misleading. What the output is for is telling you which three things to fix first.

Q02

Which standard is it for?

The questions are written against ISO 9001:2026 clause requirements, and most of them apply equally to ISO 14001, ISO 45001 and ISO 22000, because the internal audit, management review, corrective action and document control requirements are common to all four.

Q03

Two questions are marked as new. Why?

They carry the changes in the 2026 edition: opportunities managed separately from risks under 6.1.3, and a quality policy that connects to context and strategic direction under 5.2.1(e). Systems built against the 2015 edition usually answer no to both.

Q04

We answered mostly partly. What does that mean?

Usually that the system exists and the evidence does not. That is the most common position we find and it is the cheapest one to fix, because the work is organising what you already do rather than building something new.

Q05

Can we send you the result?

You do not need to. If you want a real answer, a gap analysis is one to two days on site and produces a clause-by-clause picture rather than twelve questions.

The real version takes a day

A gap analysis walks every clause against what you already do and splits it three ways: already met, met but unevidenced, and genuinely open. Most organisations are further along than twelve questions can show.

Book a gap analysis