AMC or call-out, compared on real costs

When paying per visit is cheaper, when it is not, and how to test it on last year's invoices.

A call-out arrangement pays per visit and plans nothing; an AMC pays a fixed monthly amount for planned maintenance on listed assets plus reactive cover. Call-out suits a few low-criticality assets or equipment under manufacturer cover. An AMC suits sites where downtime is expensive, assets are many, or someone will ask for the record.

Two twelve-month strips, schematic and without figures. Call-out spend is low most months with tall spikes in June, July and August, and downtime markers under those spikes. The AMC is an even band across the year.JFMAMJJASONDSUMMER PEAKCALL-OUTPER VISITDOWNTIMEAMCFIXEDPLANNED VISITS FIND THE FAULT FIRSTSCHEMATIC: SAME ASSETS, SAME YEAR, NO FIGURESAN AMC COMPETES WITH THE SPIKES AND THE DOWNTIME
The same year, paid two waysTiming and downtime, not only the totalSwipe to pan

The call-out invoice, added up

Each call-out invoice looks small until you add them up: emergency rates out of hours, no priority when every contractor's phone is ringing in July, a second visit because no parts were held, and a different technician each time with no history of the asset.

And the bill arrives in the worst month, when failures come together. A call-out arrangement concentrates both the spend and the downtime in the weeks you can least afford either.

When an AMC is poor value

An AMC is a fixed monthly figure, including the months when nothing fails. That is the point: the planned visits find the failing bearing and the blocked coil before they stop the site.

It is poor value when it is written over the wrong assets, when it maintains things that could safely run to failure, or when it produces no record, because then you are paying for visits you cannot see. The fix for all three is the same: an asset list with a criticality class on every line, agreed before the contract.

Deciding by factor

Few assets, low downtime cost, new equipment under warranty and nobody asking for records lean call-out. Many assets, expensive downtime, mid-life plant, audits, summer load and a preference for a fixed budget lean AMC.

Most sites land on both sides of this table at once, which is why the next section matters more than the table.

FactorLeans call-out · Leans AMC
Number of assetsA handful · Dozens or more
Cost of downtimeLow · High: production, tenants, cold stock, welfare
Asset ageNew, under warranty · Mid-life or older
Audit and insuranceNobody asks for records · Someone does
SeasonMild load · Summer peak load
Budget preferenceVariable and uncapped · Fixed and predictable

The hybrid most sites should use

Put class A and B assets on an AMC: the ones whose failure stops work or affects people. Leave class D assets, the cheap ones whose failure is a nuisance, on call-out or run to failure.

The criticality classes on the planned maintenance page are how that split gets made. Each asset gets a class from what its failure costs you, and the class decides which side of the line it sits on.

Test it on last year's invoices

You do not need our prices to test this. Take last year's invoices and count the call-outs, the out-of-hours premiums, the repeat visits for parts and the hours each critical asset was down. Then ask what those hours cost you.

That total is what an AMC is competing against. If it is small, stay on call-out and spend the effort elsewhere.

  • Call-outs, counted by asset
  • Out-of-hours premiums
  • Repeat visits waiting on parts
  • Hours down per critical asset, and what each hour cost

Three clinics in Khobar

A chain of three clinics in Khobar pays per call for AC and plumbing. Last summer it had repeated AC failures in treatment rooms, each costing a morning's appointments. We count the year's call-outs with the practice manager first.

We then propose an AMC over the treatment rooms' AC units, the water heaters and the pumps, and leave office lights and fittings on call-out. The clinics hold a split asset list, a PPM calendar for the critical items and a fixed monthly figure for them.

  • An asset list split into AMC and call-out candidates
  • A criticality class per asset
  • A draft PPM calendar for the AMC items
01

Questions before you sign an AMC

Q01

Is an AMC always cheaper?

No. For a handful of new assets, call-out can be cheaper. The survey tells you which side you are on.

Q02

Can we have an AMC with limited call-outs?

Yes, if the limit is written into the contract. Read it before signing, including what happens to the call-out after the limit is reached.

Q03

What if our equipment is under warranty?

The manufacturer keeps warranty work. An AMC can cover the checks the warranty allows, so the asset's record starts on day one rather than when the warranty ends.

Q04

Can we move assets between the two later?

Yes. The register and calendar are updated with a variation written before the change.

Split your assets before you choose

The walkthrough gives every asset a criticality class and puts it on one side of the line or the other.

Request an AMC scope